On a remodel, you get paid by the homeowner in draws. Your subs want to be paid the same way: some money up front, some as the work goes in, and the rest when they're done. Agreeing on that schedule before the sub starts is what keeps a good trade relationship good.
This is general information for residential work, not legal advice. Payment timing, retainage and lien rules vary by state; check yours.
A typical sub payment schedule
For a $12,000 tile job:
| Payment | When | Amount |
|---|---|---|
| Deposit | When the sub is scheduled, to cover materials and hold the date | $3,000 |
| Progress payment | When a visible stage is done (walls set, ready for grout) | $5,000 |
| Final payment | When their work is complete and has passed your punch list | $4,000 |
Smaller jobs are often just a deposit and a final. Bigger trades (framing, plumbing, electrical) may have a payment per rough-in and per trim-out.
Line it up with your own draws
The schedule only works if you have the money when the sub's payment is due. Look at your client draw schedule next to each sub's schedule: if the tile final comes due two weeks before your completion draw, you're financing it. Shifting a sub's milestones a little is usually easier than shifting the client's.
Before you pay
- Current insurance. Don't pay a sub whose general liability or workers' comp has lapsed. If someone is hurt on your job, it can become your problem. See how to read a certificate of insurance.
- A W-9 on file before the first payment, so the 1099 at year-end is easy.
- Lien waivers, where your state uses them. Many contractors collect a waiver from the sub with each payment, so the homeowner's property isn't exposed to a lien for work you've already paid for.
- The work you're paying for is done. Walk it before the final payment, not after.
Record every payment
For each payment, write down the amount, the date, and how it was paid: check number, Zelle, ACH, or something else (Venmo happens). When a sub says they never got the second payment, a check number ends the conversation. It also makes job costing possible: you can't know what a job cost if you don't know what you've paid.
Retainage
Commercial jobs often hold back 5–10% of each payment until the end. Residential remodelers mostly don't, and many simply pay the final on completion of the sub's work instead. If you do hold retainage, put it in writing in the subcontract, and check your state's rules on how much and how long.
When the bill doesn't match the bid
It happens: extra work, a material price change, a scope misunderstanding. Handle it before you pay, and in writing:
- Ask the sub what changed and why.
- If the extra work was the client's request, it belongs on a change order to the client too.
- Agree on the new amount, and keep a record of who agreed to what.
Paying subs in BuildSuite
BuildSuite keeps the sub side organized:
- Payment plans per sub per job in BuildSuite Invoicing: deposit, progress and final, with what's paid and what's left. Record each payment with the date, method (including "Other", like Venmo) and check number.
- Both sides see it. Subs on BuildSuite see the plan and can confirm a payment or record one they received, so there's no "I never got it."
- Changes to a sub's bill are proposed and approved inside the app, by either side, with the reason kept.
- Insurance and W-9 status sits next to every sub in BuildSuiteCrew, green, yellow or red, so you know before you pay.
BuildSuite Invoicing is $12.99/month and BuildSuiteCrew $9.99/month for contractors, each with a 14-day free trial. Subcontractors use BuildSuite free.