Job Costing for Remodelers: Know If a Job Made Money Before It's Over

By the BuildSuite team

Most small remodelers find out whether a job made money at tax time, if at all. By then it's too late to fix anything: the change order that never got billed, the third trip to the tile store, the sub whose final invoice came in higher than his bid.

Job costing is just comparing what a job should cost with what it's actually costing, while it's still running. You don't need accounting software for it. You need two numbers per job, checked at a few points along the way.

The two numbers

  • Planned profit: what the client agreed to pay (the signed estimate plus approved change orders) minus what you expected it to cost. This is your target.
  • Profit so far: what you've billed the client minus what the job has cost you to date: sub bills, materials, your own crew's labor, dumpsters, permits.

Use the price before sales tax for both. Sales tax isn't your money.

What goes into job cost

CostWhere the number comes from
SubcontractorsTheir bills, or what you've paid them, whichever is more
MaterialsReceipts and supplier invoices for this job, including returns as negatives
Your own crewHours on this job × what each hour actually costs you (wage plus taxes and insurance)
Job-specific extrasDumpster, permits, equipment rental, portable toilet

Leave overhead out of job cost. Overhead (insurance, trucks, office) is paid out of the margin across all jobs, which is why your markup has to be bigger than it looks. See markup vs. margin for contractors.

When to check

  • At each draw. You're already sending an invoice. Look at profit so far at the same time.
  • When a sub's bill comes in. Compare it with their accepted bid. Differences are easier to settle the week the bill arrives.
  • At closeout, before the final invoice. This is the last chance to catch an unbilled change order.

Where the margin leaks

  1. Change orders done but never billed. The most common leak. Extra work gets done on a handshake and never makes it onto paper.
  2. Allowance overages absorbed instead of billed. See allowances in remodeling contracts.
  3. Materials runs. Small purchases add up fast, and they're the ones nobody writes down.
  4. Sub bills higher than the bid, paid without a conversation.
  5. Estimating lines with no cost behind them. If a line on your estimate was priced by feel, you can't tell whether it made money. Price from cost wherever you can.

A simple job costing sheet

If you're doing it by hand, one sheet per job with these columns is enough: date, what it was for (vendor or sub), category (sub, materials, labor, other), amount. Total each category, then compare the total with your planned cost and your billing to date. Ten minutes at each draw.

Job costing in BuildSuite Invoicing

BuildSuite Invoicing keeps the numbers as you work:

  • Each job shows planned profit (signed estimates and change orders vs. their costs) and profit so far (billed vs. sub bills, sub payments and job expenses), with margin, privately. Your client never sees it.
  • Enter costs on estimate lines and your markup is added, so planned profit is there from the first draft.
  • Log materials runs, dumpsters and permits as job expenses from your phone, returns included.