Most remodeling clients sign before they've picked every faucet, light fixture and tile. An allowance is how you price those choices anyway: a set amount in the contract for an item the client will choose later. "Kitchen faucet: $400 allowance." When they choose, you compare the real price to the allowance and settle the difference.
Allowances are simple, and they're also behind a lot of end-of-job arguments. Most of those come down to three things: allowances set too low, unclear about what they include, and no agreed process for going over.
What an allowance should say
Every allowance line should answer four questions in writing:
- What it's for. "Kitchen faucet," not "plumbing fixtures."
- How much. A dollar amount, per item or per unit ("tile: $6.00 per square foot").
- Whether it's material only, or installed. This is the most common misunderstanding. If the $400 is for the faucet only, say so; installation is already in your price elsewhere.
- Whether your markup applies. If the client picks a $600 faucet, is the overage $200, or $200 plus your markup? Either is fine. Not saying is not.
Setting allowance amounts that hold up
- Price it from the client's taste, not your cheapest supplier. If they've shown you photos of designer fixtures, a builder-grade allowance just postpones the conversation, and makes your estimate look cheaper than it is.
- Use real prices from the store you'll buy from. Allowances based on last year's prices run over.
- Keep the count low. A dozen allowances on one estimate is a dozen chances for a surprise. Push the client to choose the big items before signing.
- Tie each one to a deadline. "Tile selected by the start of demo." Late selections stall the job.
When the client goes over: use a change order
When the real price comes in above the allowance, the difference is new money, and new money goes through a change order, signed before you order. Example:
| Amount | |
|---|---|
| Faucet allowance in the contract | $400 |
| Faucet the client picked | $525 |
| Change order for the overage | $125 (plus markup, if your contract says so) |
Bill the change order with the next draw (see progress billing for remodelers), not at the end of the job, when every overage adds up into one big surprise.
When the client comes in under
This one is a business decision, so put your answer in the contract:
- Credit the difference back. Common, and clients like it. A credit on a change order or the next draw keeps it clean.
- Apply it to other items or overages. Some remodelers keep the unused allowance on the job to cover other selections or unexpected costs. That's fair too, as long as the client knew it going in.
Track them while the job runs
Allowances are easy to forget until the final invoice. Keep a running list: each allowance, what the client picked, what it actually cost, and whether the change order was signed. Overages that never made it onto a change order come straight out of your profit.
Allowances in BuildSuite Invoicing
BuildSuite Invoicing handles allowances on the estimate itself:
- Mark any line as an allowance. Your client sees it labeled "Allowance" on the estimate they sign.
- When the client chooses, record what it actually came to. If it's over, a draft change order for the difference is made for you to check and send. If it's under, it's recorded.
- Approved change orders roll into the next draw invoice automatically.
BuildSuite Invoicing is in the BuildSuite HQ app for iPhone and Android, and on the web: 14-day free trial, then $12.99/month. See how it works.